Epoxy anti-static terrazzo construction instructions
Edit:Guangdong Meifule New Material Technology Co., Ltd.   PublicDate:2018-11-19

Epoxy anti-static terrazzo construction base requirements

1. Basement floor or floor without floor plan should be laid with waterproof tape (PE or PVC) before concrete construction.

2. The ground leveling layer should be cement mortar or C25 or higher fine stone slab. The mixing ratio of cement mortar screed should be in accordance with (cement: river sand: water = 1:2.5:05), and the water should not be too much to avoid Separation, it is best to collect the light within three to four hours of the mortar to ensure the bonding effect.

3. Do not sprinkle cement powder on the cement mortar when it is lighted, otherwise the surface will be roughly dense and hard, which will affect the adhesion.

4, cement mortar or fine stone screed layer thickness of at least 50mm, and strive to level, the height difference is below 1mm, with more than 28 days of maintenance and sufficient drying, the strength must reach 30Mpa or more.

5. The moisture content is below 6% before the epoxy floor material can be laid.


Epoxy antistatic terrazzo construction method


Epoxy anti-static terrazzo construction anti-static thin coating method:

1. Base finishing: After grinding and removing impurities from the plain ground with a grinding tool and roughening the concrete surface, the dust is completely cleaned with an industrial vacuum cleaner.

2. Primer coating: After the primer A/B agent is uniformly mixed according to the ratio, it is evenly coated on the base surface with a roller, and can be applied in the middle coating after about 4-8 hours.

3. Middle coating: After the A/B agent is uniformly mixed according to the ratio, add the No. 6 quartz sand and mix evenly. Spread it evenly on the primer with a serrated boring tool. After 12 hours, the conductive primer coating can be applied.

4. Install grounding copper or conductive disk.

5. Conductive primer: The conductive primer A/B agent is uniformly mixed according to the proportion, and the roller is constructed by the "ten" word intersection. The conductive primer is water-soluble. It needs to be completely dry before the construction can be applied, and the ventilation is poor. Must be forced to dry.

6, anti-static surface coating: antistatic to the coating A / B agent according to the proportion of uniform mixing, the roller "10" word cross-over construction, 12 hours after drying and repeated coating the same method.


Epoxy anti-static terrazzo construction anti-static self-leveling method

1. Base finishing: use abrasive tools to remove the impurities from the plain ground, and roughen the concrete surface, then clean the dust completely with an industrial vacuum cleaner.

2. Primer coating: After the primer A/B agent is uniformly mixed according to the ratio, it is evenly coated on the base surface with a roller, and can be applied in the middle coating after about 4-8 hours.

3. Middle coating: After the medium coating A/B agent is uniformly mixed according to the proportion, add the No. 6 quartz sand and stir evenly, and evenly lay it on the primer with a serrated trowel. After about 12 hours, the conductive primer coating can be applied.

4. Install conductive copper foil or collector board grounding according to actual conditions.

5. Conductive primer: The conductive primer A/B agent is uniformly mixed according to the proportion, and the roller is constructed by the "ten" word intersection. The conductive primer is water-soluble. It needs to be completely dry before the construction can be applied, and the ventilation is poor. Must be forced to dry.

6, anti-static surface coating: antistatic to the coating A / B agent according to the proportion of uniform mixing after the construction of the wheel "ten" word, about 48 hours after the personnel can enter, seven days after heavy machinery can enter.


Epoxy anti-static terrazzo construction note

1, the material should be placed indoors, to avoid wind and rain, if not allowed to be placed outdoors. It should not be placed for a long time. It should be stacked neatly on the pallet and covered with tape to avoid water ingress and not to be placed for a long time.

2. The material should be placed in a place where no smoking is allowed.

3. The various controls on site must be rigorous during construction.

4. Some types of materials will precipitate when stored. Please stir them evenly before use.

5. The main agent and curing agent should be weighed according to the ratio and determined to be evenly stirred.

6, humidity is above 85%, temperature below 10 °C, to avoid construction.

7, closed construction, please pay attention to air circulation.